• INFORMATIVE APPENDIXE
    BUILDING ENVELOPE TABLES

    (This appendix is not part of this code. It is merely informative and does not contain requirements necessary for conformance to the code. It has not been processed according to the ANSI requirements for a code and may contain material that has not been subject to public review or a consensus process. Unresolved objectors on informative material are not offered the right to appeal at ASHRAE or ANSI.)

    The first nine tables are in I-P units, followed by nine tables in SI units. U-factors, C-factors, F-factors, and SHGC in these tables meet the requirements of Section 701.4.2.1 (7.4.2.1), although the R-values in most cases provide more insulation than is required in Section 701.4.2.1 (7.4.2.1). These R-values represent common assemblies in building construction. Assemblies with lower R-values are allowed to be used the meet the criteria of Section 701.4.2.1 (7.4.2.1) when they meet the appropriate U-factor, C-factor, or F-factor criteria.

    TABLE E101.0 (TABLE E-0)

    (SUPERSEDES TABLE 5.5-0 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 0 (A,B)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.039R-25 c.i.U-0.032R-30 c.i.U-0.218R-3.8 c.i.
    Metal building aU-0.041R-10 + R-19 FCU-0.041R-10 + R-19 FCU-0.115R-10
    Attic and other roofsU-0.027R-38U-0.027R-38U-0.081R-13
    Walls, above grade
    Mass bU-0.580NRU-0.151R-5.7 c.i.U-0.580NR
    Metal buildingU-0.094R-0 + R-9.8 ciU-0.094R-0 + R-9.8. ciU-0.352NR
    Steel framedU-0.124R-13U-0.124R-13U-0.352NR
    Wood framed and otherU-0.089R-13U-0.089R-13U-0.292NR
    Wall, below grade
    Below-grade wallC-1.140NRC-1.140NRC-1.140NR
    Floors
    MassU-0.322NRU-0.322NRU-0.322NR
    Steel joistU-0.350NRU-0.350NRU-0.350NR
    Wood framed and otherU-0.282NRU-0.282NRU-0.282NR
    Slab-on-grade floors
    UnheatedF-0.730NRF-0.730NRF-0.730NR
    HeatedF-1.020R-7.5 for 12 in.F-1.020R-7.5 for 12 in.F-1.020R-7.5 for 12 in.
    Opaque doors
    SwingingU-0.370U-0.370U-0.700
    NonswingingU-0.310U-0.310U-1.450
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX.UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing (all)U-0.30E&W-0.21,N&S-0.221.10U-0.30E&W-0.21,N&S-0.221.10U-0.88NRNR
    Metal framing, fixedU-0.48U-0.48U-1.14
    Metal framing, operableU-0.62U-0.62U-1.14
    Metal framing, entrance doorU-0.79U-0.79U-1.05
    Skylight, 0% to 3% of roof
    All typesU-0.710.33NRU-0.710.33NRU-1.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.1 (TABLE E-1)

    (SUPERSEDES TABLE 5.5-1 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 1 (A,B)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.048R-20 c.i.U-0.039R-25 c.i.U-0.218R-3.8 c.i.
    Metal building aU-0.041R-10 + R-19 FCU-0.041R-10 + R-19 FCU-0.115R-10
    Attic and other roofsU-0.027R-38U-0.027R-38U-0.081R-13
    Walls, above grade
    Mass bU-0.580NRU-0.151R-5.7 c.i.U-0.580NR
    Metal buildingU-0.094R-0 + R-9.8 c.i.U-0.094R-0 + R-9.8. c.i.U-0.352NR
    Steel framedU-0.124R-13U-0.124R-13U-0.352NR
    Wood framed and otherU-0.089R-13U-0.089R-13U-0.292NR
    Wall, below grade
    Below-grade wallC-1.140NRC-1.140NRC-1.140NR
    Floors
    MassU-0.322NRU-0.322NRU-0.322NR
    Steel joistU-0.350NRU-0.350NRU-0.350NR
    Wood framed and otherU-0.282NRU-0.282NRU-0.282NR
    Slab-on-grade floors
    UnheatedF-0.730NRF-0.730NRF-0.730NR
    HeatedF-1.020R-7.5 for 12 in.F-1.020R-7.5 for 12 in.F-1.020R-7.5 for 12 in.
    Opaque doors
    SwingingU-0.370U-0.370U-0.700
    NonswingingU-0.310U-0.310U-1.450
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.48E&W-0.24,S-0.25,N-0.351.10U-0.48E&W-0.24,S-0.25,N-0.351.10U-0.88NRNR
    Metal framing, fixedU-0.54U-0.54U-1.14
    Metal framing, operableU-0.62U-0.62U-1.14
    Metal framing, entrance doorU-1.05U-1.05U-1.05
    Skylight, 0% to 3% of roof
    All typesU-0.710.33NRU-0.710.33NRU-1.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.2 (TABLE E-2)

    (SUPERSEDES TABLE 5.5-2 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 2 (A,B)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.039R-25 c.i.U-0.039R-25 c.i.U-0.173R-5 c.i.
    Metal building aU-0.041R-10 + R-19 FCU-0.041R-10 + R-19 FCU-0.096R-16
    Attic and other roofsU-0.027R-38U-0.027R-38U-0.053R-19
    Walls, above grade
    MassbU-0.151R-5.7 c.i.U-0.123R-7.6 c.i.U-0.580NR
    Metal buildingU-0.094R-0 + R-9.8 c.i.U-0.094R-0 + R-9.8 c.i.U-0.162R-13
    Steel framedU-0.084R-13 + R-3.8 c.i.U-0.064R-13 + R-7.5 c.i.U-0.124R-13
    Wood framed and otherU-0.089R-13U-0.089R-13U-0.089R-13
    Wall, below grade
    Below-grade wallC-1.140NRC-1.140NRC-1.140NR
    Floors
    MassU-0.107R-6.3 c.i.U-0.087R-8.3 c.i.U-0.322NR
    Steel joistU-0.038R-30U-0.038R-30U-0.069R-13
    Wood framed and otherU-0.033R-30U-0.033R-30U-0.066R-13
    Slab-on-grade floors
    UnheatedF-0.730NRF-0.730NRF-0.730NR
    HeatedF-0.900R-10 for 24 in.F-0.860R-15 for 24 in.F-1.020R-7.5 for 12 in.
    Opaque doors
    SwingingU-0.370U-0.370U-0.700
    NonswingingU-0.310U-0.310U-1.450
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.35E&W-0.24,S-0.25,N-0.351.10U-0.35E&W-0.24,S-0.25,N-0.351.10U-0.88NRNR
    Metal framing, fixedU-0.51U-0.51U-1.14
    Metal framing, operableU-0.62U-0.62U-1.14
    Metal framing, entrance doorU-0.79U-0.73U-0.79
    Skylight, 0% to 3% of roof
    All typesU-0.620.33NRU-0.620.33NRU-1.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.3 (TABLE E-3)

    (SUPERSEDES TABLE 5.5-3 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 3 (A,B,C)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.039R-25 c.i.U-0.039R-25 c.i.U-0.119R-7.6 c.i.
    Metal buildingaU-0.041R-10 + R-19 FCU-0.041R-10 + R-19 FCU-0.096R-16
    Attic and other roofsU-0.027R-38U-0.027R-38U-0.053R-19
    Walls, above grade
    MassU-0.123R-7.6 c.i.U-0.104R-9.5 c.i.U-0.580NR
    Metal buildingU-0.094R-0 + R-9.8 c.i.U-0.072R-0 + R-13 c.i.U-0.162R-13
    Steel framedU-0.077R-13 + R-5 c.i.U-0.064R-13 + R-7.5 c.i.U-0.124R-13
    Wood framed and otherU-0.089R-13U-0.064R-13 + R-3.8 c.i.U-0.089R-13
    Wall, below grade
    Below-grade wallC-1.140NRC-1.140NRC-1.140NR
    Floors
    MassU-0.074R-10 c.i.U-0.074R-10 c.i.U-0.137R-4.2 c.i.
    Steel joistU-0.038R-30U-0.038R-30U-0.052R-19
    Wood framed and otherU-0.033R-30U-0.033R-30U-0.051R-19
    Slab-on-grade floors
    UnheatedF-0.730NRF-0.540R-10 for 24 in.F-0.730NR
    HeatedF-0.860R-15 for 24 in.F-0.860R-15 for 24 in.F-1.020R-7.5 for 12 in.
    Opaque doors
    SwingingU-0.370U-0.370U-0.370
    NonswingingU-0.310U-0.310U-0.360
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.31E&W-0.24,S-0.25,N-0.351.10U-0.33E&W-0.24,S-0.25,N-0.351.10U-0.83NRNR
    Metal framing, fixedU-0.43U-0.47U-1.14
    Metal framing, operableU-0.57U-0.57U-1.14
    Metal framing, entrance doorU-0.73U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.520.33NRU-0.520.33NRU-1.62NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.4 (TABLE E-4)

    (SUPERSEDES TABLE 5.5-4 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 4 (A,B,C)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.030R-35 c.i.U-0.030R-35 c.i.U-0.088R-11 c.i.
    Metal building aU-0.035R-11 + R-19 c.i.U-0.035R-11 + R-19 c.i.U-0.078R-19 + R-6.5 c.i.
    Attic and other roofsU-0.020R-60U-0.020R-60U-0.032R-38
    Walls, above grade
    MassU-0.099R-11.4 c.i.U-0.086R-13.3 c.i.U-0.580NR
    Metal buildingU-0.057R-11 + R-13 c.i.U-0.048R-11 + R-15.8 c.i.U-0.154R-19
    Steel framedU-0.061R-13 + R-12.5 c.i.U-0.061R-13 + R-12.5 c.i.U-0.118R-13 + R-3.8 c.i.
    Wood framed and otherU-0.061R-13 + R-7.5 c.i.U-0.061R-13 + R-7.5 c.i.U-0.085R-13 + R-3.8 c.i.
    Wall, below grade
    Below-grade wallC-0.113R-10.0 c.i.C-0.087R-12.5 c.i.C-1.140NR
    Floors
    MassU-0.054R-16.7 c.i.U-0.048R-18.7 c.i.U-0.102R-8.3 c.i.
    Steel joistU-0.036R-38U-0.036R-38U-0.049R-30
    Wood framed and otherU-0.031R-38U-0.031R-38U-0.048R-30
    Slab-on-grade floors
    UnheatedF-0.494R-20 for 48 in.F-0.494R-20 for 48 in.F-0.730NR
    HeatedF-0.801R-20 for 48 in.F-0.654R-20 full slabF-0.855R-20 for 24 in.
    Opaque doors
    SwingingU-0.352U-0.352U-0.352
    NonswingingU-0.295U-0.295U-0.342
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.29E&W-0.34,S-0.36,N-0.461.10U-0.29E&W-0.34,S-0.36,N-0.461.10U-0.48NRNR
    Metal framing, fixedU-0.36U-0.36U-0.69
    Metal framing, operableU-0.44U-0.44U-0.77
    Metal framing, entrance doorU-0.65U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.480.38NRU-0.480.38NRU-1.09NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.5 (TABLE E-5)

    (SUPERSEDES TABLE 5.5-5 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 5 (A,B,C)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.030R-35 c.i.U-0.030R-35 c.i.U-0.060R-17 c.i.
    Metal building aU-0.035R-11 + R-19 c.i.U-0.035R-11 + R-19 c.i.U-0.078R-19 + R-6.5 c.i.
    Attic and other roofsU-0.020R-60U-0.020R-60U-0.032R-38
    Walls, above grade
    MassU-0.086R-13.3 c.i.U-0.076R-15.0 c.i.U-0.143R-7.5 c.i.
    Metal buildingU-0.048R-11 + R-15.8 c.i.U-0.048R-11 + R-15.8 c.i.U-0.089R-11 + R-6.5 c.i.
    Steel framedU-0.052R-13 + R-12.5 c.i.U-0.052R-13 + R-12.5 c.i.U-0.080R-13 + R-5.0 c.i.
    Wood framed and otherU-0.048R-13 + R-12.5 c.i.U-0.048R-13 + R-12.5 c.i.U-0.085R-13 + R-3.8 c.i.
    Wall, below grade
    Below-grade wallC-0.113R-10.0 c.i.C-0.087R-12.5 c.i.C-1.140NR
    Floors
    MassU-0.054R-16.7 c.i.U-0.048R-18.7 c.i.U-0.102R-8.3 c.i.
    Steel joistU-0.036R-38U-0.036R-38U-0.049R-30
    Wood framed and otherU-0.031R-38U-0.031R-38U-0.048R-30
    Slab-on-grade floors
    UnheatedF-0.494R-20 for 48 in.F-0.485R-20 for 48 in.F-0.730NR
    HeatedF-0.654R-20 full slabF-0.654R-20 full slabF-0.855R-20 for 24 in.
    Opaque doors
    SwingingU-0.352U-0.352U-0.352
    NonswingingU-0.295U-0.295U-0.342
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.29E&W-0.36,S-0.38,N-0.481.10U-0.29E&W-0.36,S-0.38,N-0.481.10U-0.43NRNR
    Metal framing, fixedU-0.36U-0.36U-0.59
    Metal framing, operableU-0.44U-0.44U-0.67
    Metal framing, entrance doorU-0.65U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.480.38NRU-0.480.38NRU-0.93NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.6 (TABLE E-6)

    (SUPERSEDES TABLE 5.5-6 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 6 (A,B)* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.030R-35 c.i.U-0.030R-35 c.i.U-0.060R-17 c.i.
    Metal building aU-0.029R-30 + R-11 LsU-0.028R-10 + R-19 + R-13 c.i.U-0.057R-10 + R-10 + R-6.5 c.i.
    Attic and other roofsU-0.020R-60U-0.020R-60U-0.032R-38
    Walls, above grade
    MassU-0.076R-15.0 c.i.U-0.067R-17.5 c.i.U-0.143R-7.5 c.i.
    Metal buildingU-0.048R-11 + R-15.8 c.i.U-0.048R-11 + R-15.8 c.i.U-0.089R-11 + R-6.5 c.i.
    Steel framedU-0.047R-13 + R-15.6 c.i.U-0.047R-13 + R-15.6 c.i.U-0.080R-13 + R-5 c.i.
    Wood framed and otherU-0.048R-13 + R-12.5 c.i.U-0.048R-13 + R-12.5 c.i.U-0.085R-13 + R-3.8 c.i.
    Wall, below grade
    Below-grade wallC-0.087R-12.5 c.i.C-0.060R-17.5 c.i.C-0.113R-10.0 c.i.
    Floors
    MassU-0.048R-18.7 c.i.U-0.048R-18.7 c.i.U-0.083R-10 c.i.
    Steel joistU-0.030R-49.0U-0.030R-49U-0.049R-30
    Wood framed and otherU-0.026R-38+ R-7.5 c.i.U-0.026R-38 + R-7.5 c.i.U-0.048R-30
    Slab-on-grade floors
    UnheatedF-0.485R-20 for 48 in.F-0.412R-15 full slabF-0.730NR
    HeatedF-0.654R-20 full slabF-0.637R-20 full slabF-0.817R-20 for 48 in.
    Opaque doors
    SwingingU-0.352U-0.352U-0.352
    NonswingingU-0.295U-0.295U-0.342
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.29E&W-0.38,S-0.40,N-0.501.10U-0.29E&W-0.38,S-0.40,N-0.501.10U-0.43NRNR
    Metal framing, fixedU-0.34U-0.34U-0.48
    Metal framing, operableU-0.43U-0.43U-0.56
    Metal framing, entrance doorU-0.65U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.480.38NRU-0.480.38NRU-0.81NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; Ls = liner system (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.4).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.7 (TABLE E-7)

    (SUPERSEDES TABLE 5.5-7 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 7* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.027R-40 c.i.U-0.027R-40 c.i.U-0.037R-26 c.i.
    Metal building aU-0.028R-10 + R-19 + R-13 c.i.U-0.028R-10 + R-19 + R-13 c.i.U-0.035R-11 + R-19 c.i.
    Attic and other roofsU-0.016R-71U-0.016R-71U-0.026R-49
    Walls, above grade
    MassU-0.067R-17.5 c.i.U-0.067R-17.5 c.i.U-0.117R-9.5 c.i.
    Metal buildingU-0.042R-11 + R-19 c.i.U-0.042R-11 + R-19 c.i.U-0.068R-11 + R-9.8 c.i.
    Steel framedU-0.047R-13 + R-15.6 c.i.U-0.040R-13 + R-18.8 c.i.U-0.061R-13 + R-12.5 c.i.
    Wood framed and otherU-0.048R-13 + R-12.5 c.i.U-0.048R-13 + R-12.5 c.i.U-0.061R-13 + R-7.5 c.i.
    Wall, below grade
    Below-grade wallC-0.060R-17.5 c.i.C-0.060R-17.5 c.i.C-0.113R-10.0 c.i.
    Floors
    MassU-0.040R-23 c.i.U-0.040R-23 c.i.U-0.070R-12.5 c.i.
    Steel joistU-0.030R-49U-0.030R-49U-0.049R-30
    Wood framed and otherU-0.026R-38 + R-7.5 c.i.U-0.026R-38 + R-7.5 c.i.U-0.048R-30
    Slab-on-grade floors
    UnheatedF-0.485R-20 for 48 in.F-0.412R-15 full slabF-0.730NR
    HeatedF-0.637R-20 full slabF-0.637R-20 full slabF-0.817R-20 for 48 in.
    Opaque doors
    SwingingU-0.352U-0.352U-0.352
    NonswingingU-0.295U-0.295U-0.295
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.27E&W-0.43,S-0.45,N-0.551.10U-0.27E&W-0.43,S-0.45,N-0.551.10U-0.30NRNR
    Metal framing, fixedU-0.31U-0.31U-0.36
    Metal framing, operableU-0.38U-0.38U-0.42
    Metal framing, entrance doorU-0.65U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.48NRNRU-0.48NRNRU-0.81NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.8 (TABLE E-8)

    (SUPERSEDES TABLE 5.5-8 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 8* (I-P)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.027R-40 c.i.U-0.027R-40 c.i.U-0.037R-26 c.i.
    Metal building aU-0.025R-19 + R-19 + R-25 c.i.U-0.025R-19 + R-19 + R-25 c.i.U-0.035R-11 + R-19 c.i.
    Attic and other roofsU-0.016R-71U-0.016R-71U-0.026R-49
    Walls, above grade
    MassU-0.046R-21.0 c.i.U-0.046R-21.0 c.i.U-0.099R-11.4 c.i.
    Metal buildingU-0.037R-11 + R-22.1 c.i.U-0.037R-11 + R-22.1 c.i.U-0.057R-11 + R-13 c.i.
    Steel framedU-0.035R-13 + R-21.9 c.i.U-0.035R-13 + R-21.9 c.i.U-0.061R-13 + R-12.5 c.i.
    Wood framed and otherU-0.030R-13 + R-21.9 c.i.U-0.030R-13 + R-21.9 c.i.U-0.048R-13 + R-12.5 c.i.
    Wall, below grade
    Below-grade wallC-0.060R-17.5 c.i.C-0.060R-17.5 c.i.C-0.113R-10.0 c.i.
    Floors
    MassU-0.036R-25.1 c.i.U-0.036R-25.1 c.i.U-0.061R-14.6 c.i.
    Steel joistU-0.030R-49U-0.030R-49U-0.049R-30
    Wood framed and otherU-0.026R-38 + R-7.5 c.i.U-0.026R-38 + R-7.5 c.i.U-0.031R-38
    Slab-on-grade floors
    UnheatedF-0.412R-15 full slabF-0.403R-15 full slabF-0.513R-20 for 24 in.
    HeatedF-0.637R-20 full slabF-0.354R-25 full slabF-0.817R-20 for 48 in.
    Opaque doors
    SwingingU-0.352U-0.352U-0.352
    NonswingingU-0.295U-0.295U-0.295
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-0.24E&W-0.43,S-0.45,N-0.551.10U-0.24E&W-0.43,S-0.45,N-0.551.10U-0.30NRNR
    Metal framing, fixedU-0.28U-0.28U-0.36
    Metal framing, operableU-0.33U-0.33U-0.42
    Metal framing, entrance doorU-0.65U-0.65U-0.73
    Skylight, 0% to 3% of roof
    All typesU-0.39NRNRU-0.39NRNRU-0.81NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.0 (TABLE E-0)

    (SUPERSEDES TABLE 5.5-0 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 0 (A,B)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.222R-4.4 c.i.U-0.184R-5.3 c.i.U-1.240R-0.7 c.i.
    Metal building aU-0.233R-1.8 + R-3.3 FCU-0.233R-1.8 + R-3.3 FCU-0.653R-1.8
    Attic and other roofsU-0.153R-6.7U-0.153R-6.7U-0.459R-2.3
    Walls, above grade
    Mass bU-3.293NRU-0.857R-1.0 c.i.U-3.293NR
    Metal buildingU-0.533R-0 + R-1.7 ciU-0.533R-0 + R-1.7 ciU-1.998NR
    Steel framedU-0.705R-2.3U-0.705R-2.3U-1.998NR
    Wood framed and otherU-0.504R-2.3U-0.504R-2.3U-1.660NR
    Wall, below grade
    Below-grade wallC-6.473NRC-6.473NRC-6.473NR
    Floors
    MassU-1.825NRU-1.825NRU-1.825NR
    Steel joistU-1.986NRU-1.986NRU-1.986NR
    Wood framed and otherU-1.599NRU-1.599NRU-1.599NR
    Slab-on-grade floors
    UnheatedF-1.264NRF-1.264NRF-1.264NR
    HeatedF-1.766R-1.3 for 300 mmF-1.766R-1.3 for 300 mmF-1.766R-1.3 for 300 mm
    Opaque doors
    SwingingU-2.101U-2.101U-3.975
    NonswingingU-1.760U-1.760U-8.233
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX.UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing (all)U-1.73E&W-0.21,N&S-0.221.10U-1.73E&W-0.21,N&S-0.221.10U-5.02NRNR
    Metal framing, fixedU-2.70U-2.70U-6.48
    Metal framing, operableU-3.51U-3.51U-6.48
    Metal framing, entrance doorU-4.48U-4.48U-5.94
    Skylight, 0% to 3% of roof
    All typesU-4.050.33NRU-4.050.33NRU-9.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.1 (TABLE E-1)

    (SUPERSEDES TABLE 5.5-1 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 1 (A,B)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.273R-3.5 c.i.U-0.220R-4.4 c.i.U-1.240R-0.7 c.i.
    Metal building aU-0.233R-1.8 + R-3.3 FCU-0.233R-1.8 + R-3.3 FCU-0.653R-1.8
    Attic and other roofsU-0.153R-6.7U-0.153R-6.7U-0.459R-2.3
    Walls, above grade
    Mass bU-3.293NRU-0.857R-1.0 c.i.U-3.293NR
    Metal buildingU-0.533R-0 + R-1.7 c.i.U-0.533R-0 + R-1.7 c.i.U-1.998NR
    Steel framedU-0.705R-2.3U-0.705R-2.3U-1.998NR
    Wood framed and otherU-0.504R-2.3U-0.504R-2.3U-1.660NR
    Wall, below grade
    Below-grade wallC-6.473NRC-6.473NRC-6.473NR
    Floors
    MassU-1.825NRU-1.825NRU-1.825NR
    Steel joistU-1.986NRU-1.986NRU-1.986NR
    Wood framed and otherU-1.599NRU-1.599NRU-1.599NR
    Slab-on-grade floors
    UnheatedF-1.264NRF-1.264NRF-1.264NR
    HeatedF-1.766R-1.3 for 300 mmF-1.766R-1.3 for 300 mmF-1.766R-1.3 for 300 mm
    Opaque doors
    SwingingU-2.101U-2.101U-3.975
    NonswingingU-1.760U-1.760U-8.233
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-2.70E&W-0.24,S-0.25,N-0.351.10U-2.70E&W-0.24,S-0.25,N-0.351.10U-5.02NRNR
    Metal framing, fixedU-3.08U-3.08U-6.48
    Metal framing, operableU-3.51U-3.51U-6.48
    Metal framing, entrance doorU-5.94U-5.94U-5.94
    Skylight, 0% to 3% of roof
    All typesU-4.050.33NRU-4.050.33NRU-9.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.2 (TABLE E-2)

    (SUPERSEDES TABLE 5.5-2 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 2 (A,B)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.220R-4.4 c.i.U-0.220R-4.4 c.i.U-0.982R-0.9 c.i.
    Metal building aU-0.233R-1.8 + R-3.3 FCU-0.233R-1.8 + R-3.3 FCU-0.545R-2.8
    Attic and other roofsU-0.153R-6.7U-0.153R-6.7U-0.300R-3.3
    Walls, above grade
    Mass bU-0.857R-1.0 c.i.U-0.701R-1.3 c.i.U-3.293NR
    Metal buildingU-0.533R-0 + R-1.7 c.i.U-0.533R-0 + R-1.7 c.i.U-0.920R-2.3
    Steel framedU-0.479R-2.3 + R-0.7 c.i.U-0.365R-2.3 + R-1.3 c.i.U-0.705R-2.3
    Wood framed and otherU-0.504R-2.3U-0.504R-2.3U-0.504R-2.3
    Wall, below grade
    Below-grade wallC-6.473NRC-6.473NRC-6.473NR
    Floors
    MassU-0.606R-1.1U-0.496R-1.5U-1.825NR
    Steel joistU-0.214R-5.3U-0.214R-5.3U-0.390R-2.3
    Wood framed and otherU-0.188R-5.3U-0.188R-5.3U-0.376R-2.3
    Slab-on-grade floors
    UnheatedF-1.264NRF-1.264NRF-1.264NR
    HeatedF-1.558R-1.8 for 600 mmF-1.489R-2.6 for 600 mmF-1.766R-1.3 for 300 mm
    Opaque doors
    SwingingU-2.101U-2.101U-3.975
    NonswingingU-1.760U-1.760U-8.233
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-2.00E&W-0.24,S-0.25,N-0.351.10U-2.00E&W-0.24,S-0.25,N-0.351.10U-5.02NRNR
    Metal framing, fixedU-2.91U-2.91U-6.48
    Metal framing, operableU-3.51U-3.51U-6.48
    Metal framing, entrance doorU-4.48U-4.15U-4.48
    Skylight, 0% to 3% of roof
    All typesU-3.510.35NRU-3.510.33NRU-9.71NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    4. b.Exception applies for mass walls above grade where the requirement is for a maximum assembly U-0.151 (see ANSI/ASHRAE/IES Standard 90.1, Section 5.5.3.2).

    TABLE E101.3 (TABLE E-3)

    (SUPERSEDES TABLE 5.5-3 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 3 (A,B,C)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.220R-4.4 c.i.U-0.220R-4.4 c.i.U-0.677R-1.3 c.i.
    Metal building aU-0.233R-1.8 + R-3.3 FCU-0.233R-1.8 + R-3.3 FCU-0.545R-2.8
    Attic and other roofsU-0.153R-6.7U-0.153R-6.7U-0.300R-3.3
    Walls, above grade
    MassU-0.701R-1.3 c.i.U-0.592R-1.7 c.i.U-3.293NR
    Metal buildingU-0.533R-0 + R-1.7 c.i.U-0.409R-0 + R-2.3 c.i.U-0.920R-2.3
    Steel framedU-0.435R-2.3 + R-0.9 c.i.U-0.365R-2.3 + R-1.3 c.i.U-0.705R-2.3
    Wood framed and otherU-0.504R-2.3U-0.365R-2.3 + R-0.7 c.i.U-0.504R-2.3
    Wall, below grade
    Below-grade wallC-6.473NRC-6.473NRC-6.473NR
    Floors
    MassU-0.420R-1.8 c.i.U-0.420R-1.8 c.i.U-0.780R-0.7 c.i.
    Steel joistU-0.214R-5.3U-0.214R-5.3U-0.296R-3.3
    Wood framed and otherU-0.188R-5.3U-0.188R-5.3U-0.288R-3.3
    Slab-on-grade floors
    UnheatedF-1.264NRF-0.935R-1.8 for 600 mmF-1.264NR
    HeatedF-1.489R-2.6 for 600 mmF-1.489R-2.6 for 600 mmF-1.766R-1.3 for 300 mm
    Opaque doors
    SwingingU-2.101U-2.101U-2.101
    NonswingingU-1.760U-1.760U-2.044
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.78E&W-0.24,S-0.25,N-0.351.10U-1.89E&W-0.24,S-0.25,N-0.351.10U-4.69NRNR
    Metal framing, fixedU-2.43U-2.64U-6.48
    Metal framing, operableU-3.24U-3.24U-6.48
    Metal framing, entrance doorU-4.15U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.970.33NRU-2.970.33NRU-9.17NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement; FC = filled cavity (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.5).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.4 (TABLE E-4)

    (SUPERSEDES TABLE 5.5-4 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 4 (A,B,C)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.173R-6.2 c.i.U-0.173R-6.2 c.i.U-0.502R-1.9 c.i.
    Metal building aU-0.200R-1.9 + R-3.3 c.i.U-0.200R-1.9 + R-3.3 c.i.U-0.442R-3.3 + R-1.1 c.i.
    Attic and other roofsU-0.113R-10.6U-0.113R-10.6U-0.183R-6.7
    Walls, above grade
    MassU-0.561R-2.0 c.i.U-0.486R-2.3 c.i.U-3.294NR
    Metal buildingU-0.324R-1.9 + R-2.3 c.i.U-0.270R-1.9 + R-2.8 c.i.U-0.874R-3.3
    Steel framedU-0.345R-2.3 + R-2.2 c.i.U-0.345R-2.3 + R-2.2 c.i.U-0.669R-2.3 + R-0.7 c.i.
    Wood framed and otherU-0.345R-2.3 + R-1.3 c.i.U-0.345R-2.3 + R-1.3 c.i.U-0.480R-2.3 + R-0.7 c.i.
    Wall, below grade
    Below-grade wallC-0.642R-1.8 c.i.C-0.496R-2.2 c.i.C-6.475NR
    Floors
    MassU-0.308R-2.9 c.i.U-0.275R-3.3 c.i.U-0.577R-1.5 c.i.
    Steel joistU-0.205R-6.7U-0.205R-6.7U-0.281R-5.3
    Wood framed and otherU-0.178R-6.7U-0.178R-6.7U-0.275R-5.3
    Slab-on-grade floors
    UnheatedF-0.855R-3.5 for 1200 mmF-0.855R-3.5 for 1200 mmF-1.264NR
    HeatedF-1.386R-3.5 for 1200 mmF-1.131R-3.5 full slabF-1.480R-3.5 for 600 mm
    Opaque doors
    SwingingU-1.997U-1.997U-1.997
    NonswingingU-1.673U-1.673U-1.943
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.67E&W-0.34,S-0.36,N-0.461.10U-1.67E&W-0.34,S-0.36,N-0.461.10U-2.75NRNR
    Metal framing, fixedU-2.05U-2.05U-3.94
    Metal framing, operableU-2.48U-2.48U-4.37
    Metal framing, entrance doorU-3.67U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.700.38NRU-2.700.38NRU-6.21NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.5 (TABLE E-5)

    (SUPERSEDES TABLE 5.5-5 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 5 (A, B, C)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.173R-6.2 c.i.U-0.173R-6.2 c.i.U-0.340R-3.0 c.i.
    Metal building aU-0.200R-1.9 + R-3.3 c.i.U-0.200R-1.9 + R-3.3 c.i.U-0.442R-3.3 + R-1.1 c.i.
    Attic and other roofsU-0.113R-10.6U-0.113R-10.6U-0.183R-6.7
    Walls, above grade
    MassU-0.486R-2.3 c.i.U-0.432R-2.6 c.i.U-0.815R-1.3 c.i.
    Metal buildingU-0.270R-1.9 + R-2.8 c.i.U-0.270R-1.9 + R-2.8 c.i.U-0.507R-1.9 + R-1.1 c.i.
    Steel framedU-0.297R-2.3 + R-2.2 c.i.U-0.297R-2.3 + R-2.2 c.i.U-0.453R-2.3 + R-0.9 c.i.
    Wood framed and otherU-0.275R-2.3 + R-2.2 c.i.U-0.275R-2.3 + R-2.2 c.i.U-0.480R-2.3 + R-0.7 c.i.
    Wall, below grade
    Below-grade wallC-0.642R-1.8 c.i.C-0.496R-2.2 c.i.C-6.475NR
    Floors
    MassU-0.308R-2.9 c.i.U-0.275R-3.3 c.i.U-0.577R-1.5 c.i.
    Steel joistU-0.205R-6.7U-0.205R-6.7U-0.281R-5.3
    Wood framed and otherU-0.178R-6.7U-0.178R-6.7U-0.275R-5.3
    Slab-on-grade floors
    UnheatedF-0.855R-3.5 for 1200 mmF-0.839R-3.5 for 1200 mmF-1.264NR
    HeatedF-1.131R-3.5 full slabF-1.131R-3.5 full slabF-1.480R-3.5 for 600 mm
    Opaque doors
    SwingingU-1.997U-1.997U-1.997
    NonswingingU-1.673U-1.673U-1.943
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.67E&W-0.36,S-0.38,N-0.481.10U-1.67E&W-0.36,S-0.38,N-0.481.10U-2.43NRNR
    Metal framing, fixedU-2.05U-2.05U-3.35
    Metal framing, operableU-2.48U-2.48U-3.78
    Metal framing, entrance doorU-3.67U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.700.38NRU-2.700.38NRU-5.29NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.6 (TABLE E-6)

    (SUPERSEDES TABLE 5.5-6 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 6 (A,B)* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.173R-6.2 c.i.U-0.173R-6.2 c.i.U-0.340R-3.0 c.i.
    Metal building aU-0.167R-5.3 + R-1.9 LsU-0.156R-1.8 + R-3.3 + R-2.3 c.i.U-0.324R-1.8 + R-1.8 + R-1.1c.i.
    Attic and other roofsU-0.113R-10.6U-0.113R-10.6U-0.183R-6.7
    Walls, above grade
    MassU-0.432R-2.6 c.i.U-0.383R-3.1 c.i.U-0.815R-1.3 c.i.
    Metal buildingU-0.270R-1.9 + R-2.8 c.i.U-0.270R-1.9 + R-2.8 c.i.U-0.507R-1.9 + R-1.1 c.i.
    Steel framedU-0.264R-2.3 + R-2.7 c.i.U-0.264R-2.3 + R-2.7 c.i.U-0.453R-2.3 + R-0.9 c.i.
    Wood framed and otherU-0.275R-2.3 + R-2.2 c.i.U-0.275R-2.3 + R-2.2 c.i.U-0.480R-2.3 + R-0.7 c.i.
    Wall, below grade
    Below-grade wallC-0.496R-2.2 c.i.C-0.340R-3.1 c.i.C-0.642R-1.8 c.i.
    Floors
    MassU-0.275R-3.3 c.i.U-0.275R-3.3 c.i.U-0.469R-1.8 c.i.
    Steel joistU-0.173R-8.6U-0.173R-8.6U-0.281R-5.3
    Wood framed and otherU-0.146R-6.7 + R-1.3 c.i.U-0.146R-6.7 + R-1.3 c.i.U-0.275R-5.3
    Slab-on-grade floors
    UnheatedF-0.839R-3.5 for 1200 mmF-0.714R-2.6 full slabF-1.264NR
    HeatedF-1.131R-3.5 full slabF-1.103R-3.5 full slabF-1.414R-3.5 for 1200 mm
    Opaque doors
    SwingingU-1.997U-1.997U-1.997
    NonswingingU-1.673U-1.673U-1.943
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.62E&W-0.38,S-0.40,N-0.501.10U-1.62E&W-0.38,S-0.40,N-0.501.10U-2.43NRNR
    Metal framing, fixedU-1.94U-1.94U-2.75
    Metal framing, operableU-2.43U-2.43U-3.18
    Metal framing, entrance doorU-3.67U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.700.38NRU-2.700.38NRU-4.59NRNR
    1. *The following definitions apply: c.i. = continuous insulation (ANSI/ASHRAE/IES Standard 90.1, see Section 3.2); NR = no (insulation) requirement; Ls = liner system (see ANSI/ASHRAE/IES Standard 90.1, Section A2.3.2.4).

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.7 (TABLE E-7)

    (SUPERSEDES TABLE 5.5-7 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 7* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.151R-7.0 c.i.U-0.151R-7.0 c.i.U-0.210R-4.6 c.i.
    Metal building aU-0.156R-1.8 + R-3.3 +R-2.3c.i.U-0.156R-1.8 + R-3.3 + R-2.3 c.i.U-0.200R-1.9 + R-3.3 c.i.
    Attic and other roofsU-0.092R-12.5U-0.092R-12.5U-0.146R-8.6
    Walls, above grade
    MassU-0.383R-3.1 c.iU-0.383R-3.1 c.i.U-0.664R-1.7 c.i.
    Metal buildingU-0.237R-1.9 + R-3.3 c.i.U-0.237R-1.9 + R-3.3 c.i.U-0.389R-1.9 + R-1.7 c.i.
    Steel framedU-0.264R-2.3 + R-2.7 c.i.U-0.227R-2.3 + R-3.3 c.i.U-0.345R-2.3 + R-2.2 c.i.
    Wood framed and otherU-0.275R-2.3 + R-2.2 c.i.U-0.275R-2.3 + R-2.2 c.i.U-0.345R-2.3 + R-1.3 c.i.
    Wall, below grade
    Below-grade wallC-0.340R-3.1 c.i.C-0.340R-3.1 c.i.C-0.642R-1.8 c.i.
    Floors
    MassU-0.227R-4.1 c.i.U-0.227R-4.1 c.i.U-0.399R-2.2 c.i.
    Steel joistU-0.173R-8.6U-0.173R-8.6U-0.281R-5.3
    Wood framed and otherU-0.146R-6.7+ R-1.3 c.i.U-0.146R-6.7 + R-1.3 c.i.U-0.275R-5.3
    Slab-on-grade floors
    UnheatedF-0.839R-3.5 for 1200 mmF-0.714R-2.6 full slabF-1.264NR
    HeatedF-1.103R-3.5 full slabF-1.103R-3.5 full slabF-1.414R-3.5 for 1200 mm
    Opaque doors
    SwingingU-1.997U-1.997U-1.997
    NonswingingU-1.673U-1.673U-1.673
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.51E&W-0.43,S-0.45,N-0.551.10U-1.51E&W-0.43,S-0.45,N-0.551.10U-1.73NRNR
    Metal framing, fixedU-1.78U-1.78U-2.05/
    Metal framing, operableU-2.16U-2.16U-2.37
    Metal framing, entrance doorU-3.67U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.70NRNRU-2.70NRNRU-4.59NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).

    TABLE E101.8 (TABLE E-8)

    (SUPERSEDES TABLE 5.5-8 IN ANSI/ASHRAE/IES STANDARD 90.1) BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 8* (SI)

    OPAQUE ELEMENTSNONRESIDENTIALRESIDENTIALSEMIHEATED
    ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**ASSEMBLYMAXIMUMINSULATIONMIN. R-VALUE**
    Roofs
    Insulation entirely above deckU-0.151R-7.0 c.i.U-0.151R-7.0 c.i.U-0.210R-4.6 c.i.
    Metal building aU-0.140R-3.3 + R-3.3 + R-4.4c.i.U-0.140R-3.3 + R-3.3 + R-4.4 c.i.U-0.200R-1.9 + R-3.3 c.i.
    Attic and other roofsU-0.092R-12.5U-0.092R-12.5U-0.146R-8.6
    Walls, above grade
    MassU-0.259R-3.7 c.i.U-0.259R-3.7 c.i.U-0.561R-2.0 c.i.
    Metal buildingU-0.210R-1.9 + R-3.9 c.i.U-0.210R-1.9 + R-3.9 c.i.U-0.324R-1.9 + R-2.3 c.i.
    Steel framedU-0.200R-2.3 + R-3.9 c.i.U-0.200R-2.3 + R-3.9 c.i.U-0.345R-2.3 + R-2.2 c.i.
    Wood framed and otherU-0.173R-2.3 + R-3.9 c.i.U-0.173R-2.3 + R-3.9 c.i.U-0.275R-2.3 + R-2.2 c.i.
    Wall, below grade
    Below-grade wallC-0.340R-3.1 c.i.C-0.340R-3.1 c.i.C-0.642R-1.8 c.i.
    Floors
    MassU-0.205R-4.4 c.i.U-0.205R-4.4 c.i.U-0.345R-2.6 c.i.
    Steel joistU-0.173R-8.6U-0.173R-8.6U-0.281R-5.3
    Wood framed and otherU-0.146R-6.7 + R-1.3 c.i.U-0.146R-6.7 + R-1.3 c.i.U-0.178R-6.7
    Slab-on-grade floors
    UnheatedF-0.714R-2.6 full slabF-0.697R-2.6 full slabF-0.888R-3.5 for 600 mm
    HeatedF-1.103R-3.5 full slabF-0.613R-4.4 full slabF-1.414R-3.5 for 1200 mm
    Opaque doors
    SwingingU-1.997U-1.997U-1.997
    NonswingingU-1.673U-1.673U-1.673
    FENESTRATIONASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGCASSEMBLYMAX. UASSEMBLYMAX.SHGCASSEMBLYMIN.VT/SHGC
    Vertical glazing, 0% to 40% of wall(for all frame types)(for all frame types)(for all frame types)
    Nonmetal framing, allU-1.35E&W-0.43,S-0.45,N-0.551.10U-1.35E&W-0.43,S-0.45,N-0.551.10U-1.73NRNR
    Metal framing, fixedU-1.56U-1.56U-2.05
    Metal framing, operableU-1.89U-1.89U-2.37
    Metal framing, entrance doorU-3.67U-3.67U-4.15
    Skylight, 0% to 3% of roof
    All typesU-2.21NRNRU-2.21NRNRU-4.59NRNR
    1. *The following definitions apply: c.i. = continuous insulation (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2); NR = no (insulation) requirement.

    2. **The insulation minimum R-value criteria in this table meet the criteria in Section 701.4.2.1 (7.4.2.1), but it is possible that some assemblies with slightly less insulation minimum R-value will also meet the criteria of Section 701.4.2.1 (7.4.2.1).

    3. a.When using the R-value compliance method for metal building roofs, a thermal spacer block is required (see ANSI/ASHRAE/IES Standard 90.1, Section 3.2).