    SECTIONM1601
    DUCT CONSTRUCTION  

    M1601.1 Duct design.

    Duct systems serving heating, cooling and ventilation equipment shall be installed in accordance with the provisions of this section and ACCA Manual D, the appliance manufacturer’s installation instructions or other approved methods.

    M1601.1.1 Above-ground duct systems.

    Above-ground duct systems shall conform to the following:

    1. 1.Equipment connected to duct systems shall be designed to limit discharge air temperature to not greater than 250°F (121°C).

    2. 2.Factory-made ducts shall be listed and labeled in accordance with UL 181 and installed in accordance with the manufacturer’s instructions.

    3. 3.Fibrous glass duct construction shall conform to the SMACNA Fibrous Glass Duct Construction Standards or NAIMA Fibrous Glass Duct Construction Standards.

    4. 4.Field-fabricated and shop-fabricated metal and flexible duct constructions shall conform to the SMACNA HVAC Duct Construction Standards—Metal and Flexible except as allowed by Table M1601.1.1. Galvanized steel shall conform to ASTM A 653.

    5. 5.The use of gypsum products to construct return air ducts or plenums is permitted, provided that the air temperature does not exceed 125°F (52°C) and exposed surfaces are not subject to condensation.

    6. 6.Duct systems shall be constructed of materials having a flame spread index of not greater than 200.

    7. 7.Stud wall cavities and the spaces between solid floor joists to be used as air plenums shall comply with the following conditions:

      1. 7.1.These cavities or spaces shall not be used as a plenum for supply air.

      2. 7.2.These cavities or spaces shall not be part of a required fire-resistance-rated assembly.

      3. 7.3.Stud wall cavities shall not convey air from more than one floor level.

      4. 7.4.Stud wall cavities and joist-space plenums shall be isolated from adjacent concealed spaces by tight-fitting fireblocking in accordance with Section R602.8.

      5. 7.5.Stud wall cavities in the outside walls of building envelope assemblies shall not be utilized as air plenums.

    TABLE M1601.1.1

    DUCT CONSTRUCTION MINIMUM SHEET METAL THICKNESS FOR SINGLE DWELLING UNITSa

    ROUND DUCT DIAMETER (inches)STATIC PRESSURE
    1/2 inch water gage1 inch water gage
    Thickness (inches)Thickness (inches)
    GalvanizedAluminumGalvanizedAluminum
    ≤ 120.0130.0180.0130.018
    12 to 140.0130.0180.0160.023
    15 to 170.0160.0230.0190.027
    180.0160.0230.0240.034
    19 to 200.0190.0270.0240.034
    RECTANGULAR DUCT DIMENSION (inches)STATIC PRESSURE
    1/2 inch water gage1 inch water gage
    Thickness (inches)Thickness (inches)
    GalvanizedAluminumGalvanizedAluminum
    ≤ 80.0130.0180.0130.018
    9 to 100.0130.0180.0160.023
    11 to 120.0160.0230.0190.027
    13 to 160.0190.0270.0190.027
    17 to 180.0190.0270.0240.034
    19 to 200.0240.0340.0240.034

    For SI: 1 inch = 25.4 mm, 1 inch water gage = 249 Pa.

    1. a.Ductwork that exceeds 20 inches by dimension or exceeds a pressure of 1 inch water gage (250 Pa) shall be constructed in accordance with SMACNA HVAC Duct Construction Standards—Metal and Flexible.

    M1601.1.2 Underground duct systems.

    Underground duct systems shall be constructed of approved concrete, clay, metal or plastic. The maximum duct temperature for plastic ducts shall not be greater than 150°F (66°C). Metal ducts shall be protected from corrosion in an approved manner or shall be completely encased in concrete not less than 2 inches (51 mm) thick. Nonmetallic ducts shall be installed in accordance with the manufacturer’s instructions. Plastic pipe and fitting materials shall conform to cell classification 12454-B of ASTM D 1248 or ASTM D 1784 and external loading properties of ASTM D 2412. Ducts shall slope to an accessible point for drainage. Where encased in concrete, ducts shall be sealed and secured prior to any concrete being poured. Metallic ducts having an approved protective coating and nonmetallic ducts shall be installed in accordance with the manufacturer’s instructions.

    M1601.2 Vibration isolators.

    Vibration isolators installed between mechanical equipment and metal ducts shall be fabricated from approved materials and shall not exceed 10 inches (254 mm) in length.

    M1601.3 Duct insulation materials.

    Duct insulation materials shall conform to the following requirements:

    1. 1.Duct coverings and linings, including adhesives where used, shall have a flame spread index not higher than 25, and a smoke-developed index not over 50 when tested in accordance with ASTM E 84 or UL 723, using the specimen preparation and mounting procedures of ASTM E 2231.

      Exception: Spray application of polyurethane foam to the exterior of ducts in attics and crawl spaces shall be permitted subject to all of the following:

      1. 1.The flame spread index is not greater than 25 and the smoke-developed index is not greater than 450 at the specified installed thickness.

      2. 2.The foam plastic is protected in accordance with the ignition barrier requirements of Sections R316.5.3 and R316.5.4.

      3. 3.The foam plastic complies with the requirements of Section R316.

    2. 2.Duct coverings and linings shall not flame, glow, smolder or smoke when tested in accordance with ASTM C 411 at the temperature to which they are exposed in service. The test temperature shall not fall below 250°F (121°C). Coverings and linings shall be listed and labeled.

    3. 3.External reflective duct insulation shall be legibly printed or identified at intervals not greater than 36 inches (914 mm) with the name of the manufacturer, the product R-value at the specified installed thickness and the flame spread and smoke-developed indices. The installed thickness of the external duct insulation shall include the enclosed air space(s). The product R-value for external reflective duct insulation shall be determined in accordance with ASTM C1668.

    4. 4.External duct insulation and factory-insulated flexible ducts shall be legibly printed or identified at intervals not longer than 36 inches (914 mm) with the name of the manufacturer, the thermal resistance R-value at the specified installed thickness and the flame spread and smoke-developed indexes of the composite materials. Spray polyurethane foam manufacturers shall provide the same product information and properties, at the nominal installed thickness, to the customer in writing at the time of foam application. Nonreflective duct insulation product R-values shall be based on insulation only, excluding air films, vapor retarders or other duct components, and shall be based on tested C-values at 75°F (24°C) mean temperature at the installed thickness, in accordance with recognized industry procedures. The installed thickness of duct insulation used to determine its R-value shall be determined as follows:

      1. 4.1.For duct board, duct liner and factory-made rigid ducts not normally subjected to compression, the nominal insulation thickness shall be used.

      2. 4.2.For ductwrap, the installed thickness shall be assumed to be 75 percent (25-percent compression) of nominal thickness.

      3. 4.3.For factory-made flexible air ducts, The installed thickness shall be determined by dividing the difference between the actual outside diameter and nominal inside diameter by two.

      4. 4.4.For spray polyurethane foam, the aged R-value per inch measured in accordance with recognized industry standards shall be provided to the customer in writing at the time of foam application. In addition, the total R-value for the nominal application thickness shall be provided.

    M1601.4 Installation.

    Duct installation shall comply with Sections M1601.4.1 through M1601.4.10.

    M1601.4.1 Joints, seams and connections.

    Longitudinal and transverse joints, seams and connections in metallic and nonmetallic ducts shall be constructed as specified in SMACNA HVAC Duct Construction Standards—Metal and Flexible and NAIMA Fibrous Glass Duct Construction Standards. Joints, longitudinal and transverse seams, and connections in ductwork shall be securely fastened and sealed with welds, gaskets, mastics (adhesives), mastic-plus-embedded-fabric systems, liquid sealants or tapes. Tapes and mastics used to seal fibrous glass ductwork shall be listed and labeled in accordance with UL 181A and shall be marked “181A-P” for pressure-sensitive tape, “181 A-M” for mastic or “181 A-H” for heat-sensitive tape.

    Tapes and mastics used to seal metallic and flexible air ducts and flexible air connectors shall comply with UL 181B and shall be marked “181 B-FX” for pressure-sensitive tape or “181 BM” for mastic. Duct connections to flanges of air distribution system equipment shall be sealed and mechanically fastened. Mechanical fasteners for use with flexible nonmetallic air ducts shall comply with UL 181B and shall be marked 181B-C. Crimp joints for round metallic ducts shall have a contact lap of not less than 1 inch (25 mm) and shall be mechanically fastened by means of not less than three sheet-metal screws or rivets equally spaced around the joint.

    Closure systems used to seal all ductwork shall be installed in accordance with the manufacturers’ instructions.

    Exceptions:

    1. 1.Spray polyurethane foam shall be permitted to be applied without additional joint seals.

    2. 2.Where a duct connection is made that is partially inaccessible, three screws or rivets shall be equally spaced on the exposed portion of the joint so as to prevent a hinge effect.

    3. 3.For ducts having a static pressure classification of less than 2 inches of water column (500 Pa), additional closure systems shall not be required for continuously welded joints and seams and locking-type joints and seams of other than the snap-lock and button-lock types.

    M1601.4.2 Duct lap.

    Crimp joints for round and oval metal ducts shall be lapped not less than 1 inch (25 mm) and the male end of the duct shall extend into the adjoining duct in the direction of airflow.

    M1601.4.3 Plastic duct joints.

    Joints between plastic ducts and plastic fittings shall be made in accordance with the manufacturer’s installation instructions.

    M1601.4.4 Support.

    Factory-made ducts listed in accordance with UL 181 shall be supported in accordance with the manufacturer’s installation instructions. Field- and shop-fabricated fibrous glass ducts shall be supported in accordance with the SMACNA Fibrous Glass Duct Construction Standards or the NAIMA Fibrous Glass Duct Construction Standards. Field- and shop-fabricated metal and flexible ducts shall be supported in accordance with the SMACNA HVAC Duct Construction Standards—Metal and Flexible.

    M1601.4.5 Fireblocking.

    Duct installations shall be fireblocked in accordance with Section R602.8.

    M1601.4.6 Duct insulation.

    Duct insulation shall be installed in accordance with the following requirements:

    1. 1.A vapor retarder having a maximum permeance of 0.05 perm [2.87 ng/(s · m2 · Pa)] in accordance with ASTM E 96, or aluminum foil with a minimum thickness of 2 mils (0.05 mm), shall be installed on the exterior of insulation on cooling supply ducts that pass through unconditioned spaces conducive to condensation except where the insulation is spray polyurethane foam with a maximum water vapor permeance of 3 perm per inch [1722 ng/(s · m2 · Pa)] at the installed thickness.

    2. 2.Exterior duct systems shall be protected against the elements.

    3. 3.Duct coverings shall not penetrate a fireblocked wall or floor.

    M1601.4.7 Factory-made air ducts.

    Factory-made air ducts shall not be installed in or on the ground, in tile or metal pipe, or within masonry or concrete.

    M1601.4.8 Duct separation.

    Ducts shall be installed with not less than 4 inches (102 mm) separation from earth except where they meet the requirements of Section M1601.1.2.

    M1601.4.9 Ducts located in garages.

    Ducts in garages shall comply with the requirements of Section R302.5.2.

    M1601.4.10 Flood hazard areas.

    In flood hazard areas as established by Table R301.2(1), duct systems shall be located or installed in accordance with Section R322.1.6.

    M1601.5 Under-floor plenums.

    Under-floor plenums shall be prohibited in new structures. Modification or repairs to under-floor plenums in existing structures shall conform to the requirements of this section.

    M1601.5.1 General.

    The space shall be cleaned of loose combustible materials and scrap, and shall be tightly enclosed. The ground surface of the space shall be covered with a moisture barrier having a minimum thickness of 4 mils (0.1 mm). Plumbing waste cleanouts shall not be located within the space.

    Exception: Plumbing waste cleanouts shall be permitted to be located in unvented crawl spaces that receive conditioned air in accordance with Section R408.3.

    M1601.5.2 Materials.

    The under-floor space, including the sidewall insulation, shall be formed by materials having flame spread index values not greater than 200 when tested in accordance with ASTM E 84 or UL 723.

    M1601.5.3 Furnace connections.

    A duct shall extend from the furnace supply outlet to not less than 6 inches (152 mm) below the combustible framing. This duct shall comply with the provisions of Section M1601.1. A noncombustible receptacle shall be installed below any floor opening into the plenum in accordance with the following requirements:

    1. 1.The receptacle shall be securely suspended from the floor members and shall be not more than 18 inches (457 mm) below the floor opening.

    2. 2.The area of the receptacle shall extend 3 inches (76 mm) beyond the opening on all sides.

    3. 3.The perimeter of the receptacle shall have a vertical lip not less than 1 inch (25 mm) in height at the open sides.

    M1601.5.4 Access.

    Access to an under-floor plenum shall be provided through an opening in the floor with minimum dimensions of 18 inches by 24 inches (457 mm by 610 mm).

    M1601.5.5 Furnace controls.

    The furnace shall be equipped with an automatic control that will start the air-circulating fan when the air in the furnace bonnet reaches a temperature not higher than 150°F (66°C). The furnace shall additionally be equipped with an approved automatic control that limits the outlet air temperature to 200°F (93°C).

    M1601.6 Independent garage HVAC systems.

    Furnaces and air-handling systems that supply air to living spaces shall not supply air to or return air from a garage.